The contract covers bridge reconstruction over the water-storage reservoir in Tallinn. The following works will be performed during the reconstruction process:
1) Repair of bridge abutments
2) Construction of the entry slab
3) Construction of the upper slab and wing walls
4) Construction of cones
Project Details
- Category: Building
- Client: Nordpont OÜ
- Project Name: Bridge reconstruction over the water-storage reservoir in Tallinn
- Сountry: Estonia
- Address: Tallinn
- Start Date: June 2023
- End Date: November 2023